top of page

EMERGENCY POWER SUPPLY SYSTEMS

Scope of work:
A leading platinum group required emergency standby power generation in the event of a total Eskom power outage. EHL was involved from the inception of the project and was appointed as the electrical and instrumentation consulting engineers.

Responsibilities included tie-in and commissioning of 21 containerised 3 MW diesel generators rated at 11 kV and 6,6 kV dependent on the plant system voltage. Generators were installed and commissioned on nine sites.

Key Facts

Client:
Leading platinum mining group

Locations:

  • Rustenburg

  • Bafokeng

  • Rasimone

  • Amandelbult

  • Modikwa

  • Twickenham

  • Union

Project summary:

  • Feasibility study

  • Construction and commissioning

  • Cost budget estimate

  • Technical Specifications

  • Technical adjudications

  • Contractor recommendation

  • Construction and commissioning

Project duration:
18 months

Project value: 
R 635 million

 

Dishaba-Amandel2 - Pic1 - Copy.JPG

Commissioning a total of 15 MW of diesel generators

Amandelbult2 15MW 1.jpg

Testing five diesel gensets in parallel

WORLD'S FIRST RURAL FUEL CELL ELECTRIFICATION TRIAL PROJECT

Key Facts

Client:
Platinum producer and fuel
cell manufacturer

Locations:
Kroonstad, Free State
Project summary:

  • EPCM of all engineering disciplines including all drawings and single line diagrams

  • Enclosure including switchgear, batteries,inverters and the PLC

  • Overhead line distribution

  • Household small power and lighting

  • Security fence and alarm system

  • Procurement packages

  • Technical evaluation and recommendation, order placement and purchasing

  • Factory and site acceptance testing,commissioning and hand-over documentation

Project duration:
12 months
Project value: 
R 15 million

Scope of work:

EHL was responsible for the full EPCM of the project. The scope of work was to build a fuel cell power generation system to conduct a 12-month trial in the rural community of Naledi Trust, Maokeng Township, Kroonstad, South Africa.


The system includes a battery bank and inverters operating within a minigrid and is designed to provide a total of 15 kW of fuel cell generated electric power. The system can generate peak power of 60 kW with the support of batteries.

Night Power Kroonstad Fuel Cell JvW.jpg

Fuel cell technology at work

0000341597_resized_fuelcell208141022duan

Commissioning in progress

SLAG CLEANING FURNACE 1 REBUILD

Scope of work:

The Slag Cleaning Furnace 1 rebuild project was to refurbish the furnace, and to make cooling modifications to optimize and increase the life cycle of the furnace and its refractory lining.

EHL was part of the feasibility study and implementation of the overall project.  The project was a great success and was fully operational in 2010.

Key Facts

Client:
Leading platinum mining group

Locations:
Platinum Mines

Project summary:

  • Pre-Feasibility

  • Design

  • Engineering

  • Execution

  • Commissioning

Project duration:
6 Years
Project value: 
R 154 million

Pic3.JPG

Success

Pic1.JPG

Inside the furnace

DEVELOPMENT OF PFDs AND P&IDs FOR AN UNDERGROUND MINE

Key Facts

Client:
Major gold mine

Location:
Carletonville, western Gauteng

Project summary:
Development of process flow diagrams
(PFDs) and piping and Instrumentation
diagrams (P&IDs) for a gold mine in the
West-Wits region

Project duration:
16 Months
Project value: 
R 1.2 million

Scope of work:

A major gold mining group required development of process flow and piping and instrumentation diagrams for the extension of an existing shaft. EHL was involved from the inception of the project and was appointed as the PFD and P&ID consulting engineers. The cost budget estimate was approved, orders placed, and equipment delivered. The final commissioning was completed in 2015.


EHL's responsibilities included consulting with various stakeholders and vendors on several processes i.e. backfill, ventilation, process water, refrigeration, ore handling and compressed air, enabling the development of the deliverables.  EHL has consequently also participated in the detailed design process for the C&I and network systems for this specific project. All P&IDs were completed using DesSoft P&ID software.

Untitled.png

Designs for an underground mine

PROCESS CONTROL SYSTEM REPLACEMENT and INPUT/OUTPUT VERIFICATION

Key Facts

Client:
Major platinum producer

Location:
Mogalakwena, Limpopo Province

Project summary:

  • Verify PLC software configuration

  • Trace and verify instrument field and I/O connections

Project duration:
3 years

Project value: 
R 28 million

Scope of work:

Our client was operating on a control system with major end-of-life or discontinued components. A decision was made to upgrade the installed control system.  The software was configured to include the latest control philosophies. To ensure faultless switch over from one control system to the other, new networks (field, inter-PLC and DCS layers) were designed, installed and commissioned prior to installation of the new panels.

 

EHL's scope included the physical tracing and verification of instruments in the plant areas selected for upgrade, re-terminating of instruments into the new control panels and updating of all instrument loop diagrams. Redundant instruments and equipment was removed. EHL was also responsible for the management of the software input/output verification and upgrade to the latest control requirements.

Untitled1.png

Redundant equipment

Untitled2.png

New Installed equipment

PLC and DCS SOFTWARE UPGRADES

Key Facts

Client:
Major platinum producer platinum

Location:
Rustenburg Platinum Mines,

Project summary:
Execution phase 

Project duration:
24 Months

Project value: 
R 25.8 million

 

Scope of work:

The Siemens S5 Programmable Logic Controller (PLC) technology was obsolete. The cost of replacement of the S5 hardware was significantly higher than the cost of a new S7 equivalent. Therefore, the Siemens S5 PLCs were upgraded to Siemens S7 PLCs. Various plant process areas were controlled from two Siemens S5 PLCs. A failure in one PLC resulted in the interruption of multiple process areas. Plant availability improved by installing additional PLCs and re-assigning plant process areas to different PLCs. This ensured a better match between plant process and PLC dependencies.

Conc Cable rack.JPG

During construction

Fibre optic & copper networks.jpg
bottom of page